First Public Session Held for Proposed EverWind AI Data Centre in Point Tupper

Representatives from the province, EverWind, and Richmond County addressed resident concerns about electricity, water, environmental oversight, and economic impacts during the first of three online information sessions on the proposed Point Tupper data centre.

The first of three online public information sessions regarding the proposed EverWind AI data centre in Point Tupper, Nova Scotia, was held on Tuesday. Representatives from the provincial government, EverWind, and Richmond County fielded questions from residents concerning electricity demand, water usage, environmental assessments, and economic impacts. Two additional online sessions are scheduled for November 18 at 7 p.m. and November 19 at 2 p.m.

Editorial illustration

To address concerns about potential strain on the electricity grid, officials stated that EverWind has agreed to an interruptible electricity rate, which requires the facility to reduce its power consumption when the system is under stress. Modelling conducted by the independent energy system operator and Nova Scotia Power indicates the grid can accommodate the increased demand. Any additional costs associated with powering the data centre will be covered by EverWind, meaning residential power bills will not increase as a result of the project.

EverWind’s proposed $10-billion investment includes wind energy development that would add at least 650 megawatts of renewable energy to the grid. Once fully operational, these wind projects are expected to cover two-thirds of the data centre’s energy needs. The first phase of the data centre is set to operate by late 2027, while the first wind farm is expected to come online in 2028.

Water usage was another key topic during the session. In its first phase, the project is expected to use an average of 100,000 litres of water per day, increasing to 500,000 litres upon the completion of both phases. By comparison, Landry Lake’s sustainable withdrawal limit is 34 million litres per day. A binding agreement with the utility ensures that drinking water for the town of Port Hawkesbury is prioritized over the data centre's cooling needs.

Editorial illustration

Officials also clarified that the data centre is not undergoing a formal environmental assessment, as other regulatory tools are being used to provide adequate oversight.

Economically, the project promises significant benefits for the region. It is expected to create over 2,000 jobs during construction and 115 permanent positions once in operation. EverWind estimates the data centre development will contribute around $2 billion to the province’s GDP during the construction phase.