Nova Scotia Power has applied to the Nova Scotia Energy Board to securitise up to $1 billion in eligible costs, including retiring coal assets. The utility estimates the plan will save customers $265 million over 30 years, though residential rates would rise 6.8% in 2027 if approved.
Nova Scotia Power has filed an application with the Nova Scotia Energy Board to finance up to $1 billion in eligible costs through securitisation. The proposal covers the remaining value of coal-related assets scheduled for retirement, fuel used to generate electricity, costs to establish the Nova Scotia Independent Energy System Operator, and other deferred expenses. 
Federal and provincial clean energy regulations require the utility to phase out and close its coal-fired electric power plants by 2030. Nova Scotia Power previously estimated unrecovered coal asset costs at around $704 million but increased the figure to $1 billion in its securitisation application.
Under the proposed framework, repayment would be spread over a 30-year period. By lowering interest rates and extending terms, the utility estimates the plan will save customers approximately $265 million compared to standard financing.
If the board approves the application, a separate line item known as a rider would appear on power bills beginning in 2027. This rider would add 2.9% for residential customers and average 3.3% across all customer groups. Combined with a previously approved 3.9% rate increase, the total increase for residential customers in 2027 would reach 6.8%.
The Province of Nova Scotia passed new regulations under the Public Utilities Act to allow Nova Scotia Power to seek approval for securitising utility assets. Premier Tim Houston stated that the decision removes politics from the discussion and gives the independent board authority to determine if it benefits ratepayers. 
Opposition parties have criticised the move. NDP leader Claudia Chender described the plan as a $1 billion bailout that forces Nova Scotians to pay for the early retirement of coal assets. Interim Liberal Leader Iain Rankin argued that securitisation changes how costs are paid but does not erase them, and he criticised the delay in implementing the measure.